A/A Sector Sub-sector Project name Implementin Description Included in Status Total Investment Barriers/solutions
g agency national investment in 2015 –
investment plan cost (EUR 2017 (EUR
(yes/no) bn) bn)
1 Energy Energy Energy Ministry of The project concerns public, residential and commercial buildings Part of the cost Implementation 2.4 Lack of funding
Union Efficiency in Efficiency Env (~400m public schedule 2014-
inironment, with a view to implement interventions improving energy
Buildings Buildings Energy and performance. Priotity should be given to buidlings (in all the above expences) will be 2020
Climate mentioned sectors) with poor energy performance. Financing through covered by the
Change ESCO's is also included. structural funds
(programming
period 2014-
2020)
2 Knowledge ICT Development of HEDNO The project concerns the replacement of existing metering systems Part of the cost 2013-2020 1 Lack of funding
and the Infrastructure "smart meters" with new "smart" ones that take full advantage of ICT (~24.7m public
digital and "smart expences) will be
economy grids" covered by the
structural funds
(7.8m by the
programming
period 2007-2013
and the rest by
the programming
period 2014-
2020)

3 Energy Connections Interconnection IPTO Construction of a new AC 400 kV single-circuit interconnector (OHL) Potential funding 2015-2020 0.01 Lack of funding
Union and production between Maritsa with a length of 130 km and a capacity of 2000 MVA between under CEF
East 1 (BG) and Maritsa East 1 (BG) and Nea Santa (EL) (onshore)
N. Santa (EL)


4 Energy Connections Euro Asia PPC Quantum The project consists of a 600 kV DC underwater electric cable and Potential funding 2015-2020 1 Lack of funding
Union and production Interconnector Energy Ltd - any essential equipment and/or installation for interconnecting the under CEF
IPTO Cypriot, Israeli and the Greek transmission networks (offshore). The
project will have a capacity of 2000 MW and a total length of around
820 nautical miles/around 1518 km (329 km between CY and IL, 879
km between CY and Crete and 310 km between Crete and Athens)
and allow for reverse transmission of electricity.




5 Energy Connections Hydro-pumped TERNA Pumped Storage Complex with two independent upper reservoirs: Potential funding 2015-2020 0.5 Lack of funding
Union and production storage in Agios Georgios and Pyrgos, using as lower reservoir the artificial under CEF
Greece - reservoir of Kastraki (owner Public Power Corporation). The
Amfilochia equipment for energy production and energy pumping will be
installed in two independent power houses, near Kastraki reservoir.